Preparation:
Site Assessment: Evaluate the site to ensure there is enough space and the ground is stable for the dismantling process.
Permits and Notifications: Obtain necessary permits and inform local authorities and nearby residents about the dismantling schedule.
Lowering the Jib:
Remove Counterweights: Start by removing the counterweights from the jib to balance the crane.
Disassemble the Jib: Carefully lower and disassemble the jib sections using a mobile crane.
Dismantling the Mast:
Hydraulic Jacking System: Use the hydraulic jacking system to lower the mast sections one by one.
Remove Mast Sections: Each section is unbolted and lowered to the ground using a mobile crane.
Base Removal:
Disconnect Power: Ensure all power sources are disconnected.
Remove Anchors: Unbolt the base from the concrete foundation.
Lift the Base: Use a mobile crane to lift and remove the base.
Safety Measures:
Clear Communication: Maintain clear communication between all team members using radios or hand signals.
Weather Conditions: Avoid dismantling in adverse weather conditions to prevent accidents.
Regular Inspections: Conduct regular inspections of equipment and tools to ensure they are in good condition.
Professional Team: Always hire a professional team with experience in dismantling tower cranes.
Documentation: Keep detailed records of the dismantling process for future reference and compliance.